The capital has a well -known university. University Auditorium. Auditorium condition ..! Where the situation is in bad shape, where there are questions arising on the system by looking at each scene.
Satya Rajput, Raipur. The auditorium under construction of Kushabhau Thackeray Journalism University in the capital is indeed an auditorium or corruption building, it can be gauged only by looking at the picture of the wall of the building under construction. This auditorium has been built at a cost of crores, although this Navnirman building has not yet been inaugurated and thus the case of large scale corruption has been exposed here.
In fact, the team of Lalluram.com arrived at the Journalism University in Kethadih in the capital today. During this time, the huge building seen behind acacia, plum, other prickly trees and bells inside the university campus is not a ruin. Looking at it, it seems as if it is decades old. But its reality is something else. According to Journalism University Management, this auditorium is still under construction. The surprising thing is that when it is under construction, how did it reach the state of fall? There is a wall of the auditorium built behind the administrative building of the university, which has already been inaugurated before the inauguration. The construction work has not been completed yet. In such a situation, many questions are also arising due to the crack in the wall, cracks in the beam and the fall of interior design.
7 crore monkey bond?
RUSA (National Higher Shiksha Abhiyan) has created an auditorium at Journalism University at a cost of seven crores. The thing to think is that the purpose with which the auditorium has been created. Even after 7 years of the formation of the auditorium, there is not a single program in it. In the situation in which the tourism is still there, it will not take any time to get frozen.
Handover screw
According to the National Higher Education Campaign Office, in 2018, the auditorium has been completed here. A letter has been issued to the University of Journalism to give a handover. But according to the information received from the university, Kushabhau Journalism University had got it but we have not taken a handover. Because the internal work is remaining in the auditorium which will do PWD. Therefore the handover has not been taken.
Nadrad was seen responsible
Kushabhau Thackeray reached the office of Lalluram.com to take answers from Baldev Bhai Sharma, Vice Chancellor of Journalism University, to know why the auditorium ruins at Journalism University are turning into ruins. There was a lock in his office, when a call was made to contact him, he did not reply to the call.
Work remains – Registrar
Registrar Sunil Sharma said that a letter has been written to RUSA for the repair work of the auditorium. The handover has not been taken to the auditorium due to incomplete work. PWD work remains in this.
Assurance of investigation
Rusa Director Jagdish Sonkar said that since I have just joined RUSA, I find out the matter, talk to the university registrar and get it investigated immediately, then you will know what is the matter.
RUSA and Journalism University Management in the dock?
Now the question arises that when the auditorium was not required, why was it made?
Why did the monkeybant of 7 crores not be investigated?
The auditorium made at Journalism University is turning into ruins, yet why is the management silent?
Instead of demanding the repair amount instead of demanding action, what is the reason behind the demand for action?
When the work was incomplete, why did PWD, RUSA and University management remain silent for the last seven years?