Key Milestones Achieved in Maharashtra Section of India's First Bullet Train
Significant progress has been recorded in the Maharashtra stretch of the Mumbai‑Ahmedabad bullet train, as highlighted by the rail ministry. The elevated corridor, running from Shilphata to the Jaroli village on the state border, measures 135.45 kilometres and is a backbone of the high‑speed network.
Out of the seven tunnels being excavated through the Western Ghats, three have already seen full breakthrough, linking both portals. Drainage systems, waterproofing membranes and concrete lining are now being installed, moving the tunnels toward final fit‑out.
In the viaduct segment, more than 100 kilometres of pillars have been laid, with 74 kilometres fully completed and ready for girder placement. This work paves the way for the uninterrupted flow of trains across the elevated track.
The construction programme is supported by nine dedicated casting yards and a fleet of launch gantries—seven full‑span and eight span‑by‑span—ensuring concrete components are fabricated and positioned efficiently.
Infrastructure also includes major river crossings: a 460‑metre bridge over the Ulhas, a 2.32‑kilometre viaduct over the Vaitarna, and a 510‑metre bridge on the Jagani River, complemented by 36 other bridges and 12 steel bridges that will span existing rail lines and highways.
These milestones underscore the project's ambition to deliver a world‑class high‑speed rail corridor that will cut travel time dramatically and boost regional economic activity.